· Completed the production import of 2 automatic lines 2.0
· One line produces 3812 and one line 3511
· The automation line is currently carrying out 3511 production verification combined with 2-in-1 shielding box equipment
· Collected and counted the problem points of automatic line 2.0 as the optimization experience in the next stage
· Collect and statistics the problem points of automatic line 2.0 to avoid them in the next stage of equipment upgrade
· Introduced several automation debugging engineers
Set up rf test lab and OTA antenna test lab, which integrates antenna/RF simulation, RF test and antenna test
Set up failure analysis laboratory for device level failure analysis
Set up audio testing laboratory, audio simulation, audio testing as a whole, to serve customers with high audio quality requirements for professional audio system design
Set up image testing and analysis laboratory for camera products